Achievements

Renovatio Solar completed the first industrial sized photovoltaic parks in Romania:


Singureni Photovoltaic Park - 1 MW

Located in the southern part of the country, Singureni Photovoltaic Park is the first 1 MW solar park constructed in Romania, as well as the first park constructed and operated by Renovatio.

Capacity: 1 MW.
Number of panels: 4176.
Panel Capacity: 240 wp
Electrical Connection: T-Connection to a 20 kv line.
Location: Giurgiu County, Romania.

Current status
Start of construction: May 2010.
Commissioning: End of 2010.


Scornicesti Photovoltaic Park - 1MW

Scornicesti Photovoltaic Park is the second solar park to be operated by Renovatio in the country with a capacity of 1 MW. It is located in Olt County in Romania.

Capacity: 1 MW.
Number of panels: 4176.
Panel Capacity: 240 wp
Electrical Connection: Connection to existing substation.
Location: Olt County, Romania.

Current status
Start of construction: Q3 2011.
Commissioning: Q4 2011.


Crevedia Photovoltaic Park - 2 MW

Located in the southern part of the country 30km from Bucharest, Crevedia Photovoltaic Park is the third MW solar park constructed in Romania, as well as the third park constructed by Renovatio.

Capacity: 2 MW.
Number of panels: 8400.
Panel Capacity: 245 Wp
Electrical Connection: T-Connection to a 20 kv line.
Location: Dambovita County, Romania.

Current status
Under construction


Corabia Photovoltaic Park - 7 MW

Located in the southern part of the country, Corabia Photovoltaic Park will be the forth MW solar park constructed in Romania, as well as the forth park constructed by Renovatio.

Capacity: 7 MW.
Number of panels: 28602.
Panel Capacity: 245 Wp
Electrical Connection: T-Connection to a 20 kv line.
Location: Olt County, Romania.

Current status
Under construction

Copyright 2012 © Renovatio Solar. All rights reserved.